Wells supplied all of the labour, including I&E supervision, required for the instrumentation and electrical installation during the construction of the Stratford Peaker Power Station. A 15 month 75,000 man-hour project...

STRATFORD PEAKER POWER STATION

 

Wells provided instrumentation and electrical installation services during the construction of the Stratford Peaker Power Station in Stratford, Taranaki. Supplying I&E supervision and covering all labour requirement in this area.

11KV Bus Duct running between Gas Turbine and 11KV to 220KV step up transformer
Balance of plant main 400V switch board installed by Wells

Photo: 11KV Bus duct running between Gas Turbine and 11KV to 220KV step up transformer.

Photo: Balance of plant main 400V switch board installed by Wells.

This was a 15 month, 75,000 man-hour project to complete all of the electrical and instrumentation works associated with the installation of two 100 MW gas turbine units which are designed for fast start and high efficiency, enabling them to respond to variations in output from wind and hydroplants. At the peak of construction Wells I&E had 90 people on the site.