Maui-A Produced Water project. Truck with crane on platform.

MAUI-A PRODUCED WATER

 

Wells provided I&E services to Shell Todd Oil Services (STOS) for the construction phase of the MPA
off-shore produced water project...

For more information about Wells projects

 

The project ran for 12 months and utilised 25 Wells off-shore electricians, instrument technicians and construction engineers. Wells provided the construction labour resources that carried out the installation, commissioning and testing of the entire project.

 

The work done included installing cable support systems, cables, junction boxes, terminations  and MCC modules, commissioning and QA documentation Work was also done on the MAGLOG system as well as instrumentation work and commissioning.

Maui-A Platform

Photo: View from helicopter landing pad on Maui A platform.

The work was challenging for the 2 week on 2 week off rostered staff due to the unique nature of projects on a producing gas platform. The ‘can do’ attitude of the Wells staff in carrying out the work meant commitment to a successful project .This commitment even led to staff staying on during their rostered time off to achieve the required completion. The project was delivered to the client’s requirements, incident free.